infrastructure 17 September 2026 The Observer (Uganda)

Busega-Mpigi Expressway: 14 Fatal Decisions Led to Massive Cost Overruns

The Busega-Mpigi Expressway project, initially budgeted at Shs 547 billion, is now projected to cost Shs 1.3 trillion due to a series of critical errors in decision-making, corruption, and mismanagement within the Uganda National Roads Authority (UNRA). An investigation reveals that out of 16 key decisions made since 2015, only two were executed correctly, leading to severe financial and logistical problems. Source: https://observer.ug/news/how-14-fatal-decisions-bungled-up-busega-mpigi-expressway

The ambitious Busega-Mpigi Expressway project, intended to connect Kibuye, Busega, and Mpigi, has become a cautionary tale of mismanagement. What began as a Shs 547 billion undertaking, financed by the African Development Bank (AfDB), is now on track to cost a staggering Shs 1.3 trillion. An in-depth analysis of the project’s inception in 2015 highlights 16 crucial decisions, with a distressing 14 found to be fundamentally flawed, leading to significant cost escalations and delays.

One of the earliest and most detrimental decisions involved tendering the civil works before the design was finalized. Despite warnings from UNRA’s own planning and engineering directorate and recommendations from the financier, top management proceeded with the tender based on an incomplete design. This critical sequencing error was compounded by a failure to reconcile scope changes with the design. The AfDB introduced four interchanges onto the Busega-Mpigi section, but no corresponding detailed design was commissioned before the bidding process commenced.

Further complicating matters, the project’s procurement process was initiated without proper authorization and oversight. Decisions to proceed with tendering were made by both the top management and the accounting officer, overriding warnings about the incomplete design. The Contracts Committee, chaired by the same official who authored the tender documents, approved the bidding documents, creating a clear conflict of interest.

The AfDB’s own “no-objection” to the tender documents, despite acknowledging the design inadequacies, remains a point of concern. A subsequent realignment of the road corridor, initiated in late 2017, added another layer of complexity. Critically, this significant design change was never disclosed to the bidders. Consequently, contractors submitted bids based on an outdated design, paving the way for future claims and cost increases when the actual construction began on the altered alignment.

These cumulative errors, including the failure to update bid documents and extend bidding periods after design changes, have severely undermined the project’s integrity and financial predictability. The approved Resettlement Action Plan update for the new alignment, while executed correctly, came after the damage had already been done, highlighting a pattern of reactive rather than proactive problem-solving. The full implications of these decisions are still unfolding as the project progresses under immense financial strain.

Source: The Observer (Uganda)